Calculate Eichleay formula damages for unabsorbed home office overhead from contract billings, total company billings, overhead and delay days.
Calculator Functions
| Function | What it does | What it requires |
|---|---|---|
| Eichleay damages | Finds the unabsorbed home office overhead for a delayed contract, along with the allocation ratio, the overhead allocable to the contract and the daily contract overhead | Requires the contract billings, total company billings and total home office overhead for the same period, the total contract performance days and the compensable delay days |
All three dollar amounts must cover the same contract performance period. Contract billings cannot be larger than total company billings, and the calculator adds a caution when the delay days exceed the contract days.
Eichleay Formula
| AO | Overhead allocable to the contract ($) |
| CB | Contract billings ($) |
| TB | Total company billings for the contract period ($) |
| OH | Total home office overhead for the contract period ($) |
| DO | Daily contract overhead ($ per day) |
| CD | Days of contract performance |
| DD | Days of compensable delay |
| ED | Eichleay damages ($) |
These are the three steps the U.S. Court of Appeals for the Federal Circuit sets out: share out the overhead by billings, turn the contract’s share into a daily rate, then multiply by the days of delay [1]. With $1,000,000 of contract billings out of $10,000,000 in total billings and $2,000,000 of home office overhead, the allocation ratio is 10% and the allocable overhead is $200,000. Over 395 contract days that is $506.33 a day, and 30 days of compensable delay comes to $15,189.87.
Home office overhead is the indirect cost of running the whole business, which cannot be charged to one contract. It goes unabsorbed when a delay cuts the stream of direct costs it would normally be spread across [1]. The formula estimates that amount as a daily overhead rate for the contract times the days of delay [2].
Limits of This Estimate
- The result is arithmetic, not an entitlement. Whether an Eichleay claim is allowed depends on the contract and the jurisdiction.
- In federal contract cases the contractor must first show a government-caused delay of uncertain length, that performance was extended, and that it was kept on standby and could not take on other work [1] [2].
- The Federal Circuit treats Eichleay as the exclusive formula only where work on the contract had begun. A contractor whose performance never started may have to allocate overhead another way [1].
- The answer is only as good as the periods behind it. Billings, overhead and contract days must all cover the same period, and the contract days normally include the delay.
Sources
- U.S. Court of Appeals for the Federal Circuit, Nicon, Inc. v. United States, No. 02-5097 (2003): the three steps of the formula, what unabsorbed overhead is, and when the formula applies
- U.S. Court of Appeals for the Federal Circuit, Mech-Con Corp. v. West, No. 95-1048 (1995): the formula as a daily rate times days of delay, and the standby requirements
