Calculate delay percentage from total delay and total time, planned vs actual duration, or delayed tasks as a share of total tasks overall.

undefined

Delay Percentage Formula

The calculator uses one of three formulas depending on the mode you select.

Delay time mode:

Delay % = (Delay time / Total time) × 100

Plan vs actual mode:

Delay % = ((Actual duration − Planned duration) / Planned duration) × 100

Tasks mode:

Delay % = (Delayed tasks / Total tasks) × 100
  • Delay time — total time lost to delays.
  • Total time — full window the delay is measured against.
  • Planned duration — scheduled or expected time to complete the work.
  • Actual duration — time the work actually took.
  • Delayed tasks — tasks that finished late.
  • Total tasks — every task in scope, late or on time.

Delay time and total time must use the same unit before dividing. The calculator converts units automatically. In plan vs actual mode, a negative result means the work finished early. Task counts must be whole numbers no larger than 9,007,199,254,740,991; the total must be positive.

Reference Tables

The first table shows illustrative site-defined bands, not universal project or industry benchmarks. The widget reports the percentage without assigning these ratings.

Delay % Status Typical reading
0%On timeNo measurable delay.
> 0% to 5%LowIllustrative low band; significance depends on the project.
> 5% to 15%ModerateWorth investigating the cause.
> 15%HighIllustrative high band; assess the causes and context.
NegativeAheadPlan vs actual only — finished before plan.
Unit Equals (seconds)
1 millisecond0.001
1 second1
1 minute60
1 hour3,600
1 day86,400

Worked Examples

Delay time: A flight loses 12 minutes over a 120-minute trip. 12 ÷ 120 × 100 = 10% delay.

Plan vs actual: A task planned for 8 hours takes 9.5 hours. (9.5 − 8) ÷ 8 × 100 = 18.75% overrun.

Tasks: 6 of 40 tasks finish late. 6 ÷ 40 × 100 = 15% delayed.

Can the result be more than 100%? Only in plan vs actual mode. If actual duration is double the plan, the delay percentage is 100%. Delay time and tasks modes are capped at 100% because the part cannot exceed the whole.

What if there is no delay? The result is 0%. In plan vs actual mode, a negative result means the work finished ahead of schedule.