Estimate demolition cost for a house or building from its square footage using a typical cost per square foot or your local rate, plus disposal costs.
Related Calculators
- Gross Floor Area Calculator
- Waste Factor Calculator
- House Weight Calculator
- Building Coverage Calculator
- All Construction Calculators
Calculator Functions
| Function | What it does | What it requires |
|---|---|---|
| Total demolition project cost | Estimates the full cost of a teardown from its area, a rate per unit area and a site access factor, then adds contingency, markup and any listed extra costs | Requires the demolition area, a demolition rate and the site access factor |
| Base rate for a target total budget | Finds the highest base rate per square foot or square meter that a fixed budget can cover | Requires the demolition area, the target total budget in USD and the site access factor |
Area goes in as square feet or square meters. The demolition rate is a preset of about $7 per sq ft for a typical house teardown, $5 with the foundation left in place or $15 for an urban or high-cost teardown, or a custom local rate per sq ft or per mยฒ. The site access factor is 1.00 for open access, 1.10 for typical, 1.25 for restricted and 1.50 for very difficult access. Optional settings add debris hauling and disposal, permits and utility disconnects, hazardous-material work, foundation removal, other direct costs, a salvage or recycling credit, contingency (10% unless changed) and contractor markup (0% unless changed). Each result lists every cost line and the effective cost per sq ft or mยฒ.
Demolition Estimate Formulas
(1 + m) โ S
| T | Total estimated project cost (USD) |
| B | Base demolition cost, B = A ร r ร x |
| A | Demolition area (sq ft or mยฒ) |
| r | Demolition rate per unit of area, in the same area unit as A |
| x | Site access factor, 1.00 to 1.50 |
| F | Added direct costs: disposal, permits, hazardous-material work, foundation removal and other costs (USD) |
| c | Contingency as a fraction, 0.10 for 10% |
| m | Contractor markup as a fraction, 0.20 for 20% |
| S | Salvage or recycling credit (USD) |
Total demolition project cost
The main formula applies directly. Contingency is applied to the base demolition cost plus the added direct costs, markup is applied after contingency, and the salvage credit comes off last. A 2,000 sq ft house at the $7 preset with open access and the 10% contingency gives B = 2,000 ร 7 ร 1.00 = $14,000 and T = 14,000 ร 1.10 = $15,400, or $7.70 per sq ft. Adding $5,000 of direct costs, a 20% markup and a $1,000 salvage credit gives (14,000 + 5,000) ร 1.10 ร 1.20 โ 1,000 = $24,080.
Base rate for a target total budget
(1 + m)) โ F) รท (A ร x)
This is the main formula solved for the rate. A $30,000 budget for 2,000 sq ft with open access, the 10% contingency and no added costs allows r = 30,000 รท 1.10 รท 2,000 = $13.64 per sq ft. A budget that only just covers the added costs returns a rate of zero, and a smaller budget is rejected.
Demolition Cost per Square Foot
House demolition in the United States costs $4 to $17 per square foot as of October 2026, with a national average of $15,800 for a whole house [1]. The three presets of $5, $7 and $15 per sq ft sit inside that range and are planning figures, not quotes. One square foot is 0.09290304 mยฒ, so $7 per sq ft is about $75.35 per mยฒ. The table shows base demolition cost, before contingency and added costs, at the low end, the typical preset and the high end.
| Area (sq ft) | At $4 per sq ft | At $7 per sq ft | At $17 per sq ft |
|---|---|---|---|
| 1,000 | $4,000 | $7,000 | $17,000 |
| 1,500 | $6,000 | $10,500 | $25,500 |
| 2,000 | $8,000 | $14,000 | $34,000 |
| 2,500 | $10,000 | $17,500 | $42,500 |
| 3,000 | $12,000 | $21,000 | $51,000 |
How to Estimate Demolition Costs
Measure the floor area to be demolished and multiply it by a local rate per square foot or square meter, then by an access factor above 1.00 if the site is tight. Add the costs the rate does not already include: debris hauling and disposal, permits and utility disconnects, foundation removal, and removal of asbestos-containing material, which has to be handled properly before a building comes down [2]. Add a contingency for unknowns, apply the contractor markup if the rate excludes it, and subtract any credit for salvaged or recycled material.
Limits of This Estimate
- This is a preliminary budget, not a bid. The preset rates are US planning averages, and local quotes vary widely with home size, location and materials [1]. These estimates are based on the best available data and estimations.
- The site access factors of 1.00 to 1.50 are illustrative multipliers, not an industry pricing standard, and they apply to base demolition only.
- A cost already included in a contractorโs rate should not be entered again as an added cost, and markup already in the rate should stay at 0%.
- Hazardous-material work is entered as a quoted allowance. The calculator does not assess whether asbestos, lead or other hazardous materials are present, and these need qualified testing and licensed handling [2].
Sources
- Angi, How Much Does It Cost to Demolish a House?: demolition cost per square foot and the national average, updated October 13, 2026
- U.S. EPA Region 5, On the Road to Reuse: Residential Demolition Bid Specification Development Tool: asbestos handling, waste disposal and salvage as parts of a demolition job
