Estimate how long an excavation takes in hours and workdays from dig volume and excavator production rate, or from bucket size and cycle time.

Use 100% if the entered rate already includes job delays.

Optional settings
Only for delays not already covered by job efficiency.

Calculator Functions

FunctionWhat it doesWhat it requires
Time from rated productionFinds the hours and scheduled workdays needed to dig a volume at a rated production rateRequires the excavation volume, the production rate, the job efficiency and the scheduled work hours per day
Time from bucket cyclesFinds the digging time from the bucket size and how long each bucket cycle takesRequires the excavation volume, rated bucket capacity, bucket cycle time, bucket fill factor, job efficiency and scheduled work hours per day
Average measured production rateFinds the average production rate from work already doneRequires the volume excavated and the elapsed work time
Volume from effective productionFinds the volume that can be dug in a set timeRequires an effective production rate, one that already includes delays, and the work time

Volumes can be entered in m³ or yd³ and rates in m³/h or yd³/h, with 1 yd³ taken as 0.7646 m³ [2]. Job efficiency starts at 80%, bucket fill factor at 90% and the workday at 8 hours. The two time functions also take an optional additional time contingency, as a percentage, for delays that the job efficiency does not already cover.

Excavation Time Formulas

ET = V ÷ (M × E) × (1 + U)
ETExcavation time (hours)
VVolume to excavate (m³)
MRated production of the machine (m³/h)
EJob efficiency as a decimal, 0.80 for 80%
UAdditional time contingency as a decimal, 0.10 for 10%

The U.S. Army’s earthmoving manual builds its estimates the same way: the net production rate is the maximum rate times an efficiency factor, and the time required is the amount of work divided by that rate [1]. Its efficiency factor is the working minutes in an hour divided by 60, and it expects about 50 working minutes per hour, a factor of 0.83, on a well-managed job [1].

Time from rated production

For 500 m³ at a rated 50 m³/h and 80% efficiency, the effective production is 40 m³/h and the dig takes 12.5 hours. A 10% contingency raises that to 13.75 hours, which is 1.71875 workdays of 8 hours. Workdays are hours divided by the scheduled hours per day, and a part day is not rounded up.

Time from bucket cycles

M = B × F × 3,600 ÷ CT [1]

B is the rated bucket capacity, F is the bucket fill factor as a decimal and CT is the cycle time in seconds, so 3,600 ÷ CT is the number of cycles in an hour. A 1.5 m³ bucket at a 90% fill factor on a 20 second cycle is rated at 243 m³/h. At 80% efficiency that is 194.4 m³/h, and 1,000 m³ takes 5.14 hours. The Army manual works a bucket estimate the same way: a 0.75 yd³ bucket on a 40 second cycle in a 50-minute hour produces about 56 yd³ an hour, so 450 yd³ takes 8 hours [1].

Under average conditions the manual puts an excavation cycle at 14 seconds for hoes with buckets under 1 yd³ and 15 seconds for buckets from 1 to under 2.5 yd³, with deeper cuts and wider swings taking longer [1]. Its fill factors for wheel loader buckets run from 0.60 to 0.75 for poorly blasted rock, 0.80 to 1.00 for soil and 1.00 to 1.10 for moist loam [1].

Average measured production rate

P = V ÷ T

P is the average production and T is the elapsed work time. If 600 m³ came out in 8 hours of work, the average was 75 m³/h, or 98.1 yd³/h. Because T includes every stoppage in those hours, this is an effective rate.

Volume from effective production

V = P × T

At an effective 40 m³/h, 6 hours of work moves 240 m³, or 313.9 yd³. No efficiency is applied here, so the rate entered must already allow for delays.

Limits of This Estimate

  • Keep the volume, the bucket and the rate on the same basis. Soil takes up more room once it is dug, and the Army manual separates bank, loose and compacted cubic yards for that reason [1]. The calculator applies no swell or shrink factor.
  • Job efficiency and the contingency both add time. A delay counted in one should not be counted again in the other.
  • Each estimate holds one production rate for the whole job. Changes in material, depth, access, haul trucks and weather alter the real rate.
  • Fill factors and cycle times quoted here are averages from one manual. A machine’s own performance data or a timed cycle on site is better. These estimates are based on the best available data and estimations.

Sources

  1. U.S. Army, Field Manual 5-434, Earthmoving Operations (June 2000): production rate and time required, efficiency factor, bucket production, cycle times, fill factors and volume states
  2. NIST, Special Publication 811, Guide for the Use of the SI, Appendix B.8: cubic yard to cubic meter conversion