Calculate welding time from weld length and travel speed, or solve for length or speed. Add passes, parts, and arc-on factor for practical job estimates.
Related Calculators
- Weight Per Foot Calculator
- Relative Wall Thickness Calculator
- Plate Deflection Calculator
- Factor of Safety Calculator
- All Construction Calculators
Calculator Functions
| Function | What it does | What it requires |
|---|---|---|
| Welding time | Finds the arc-on time for a weld, or the working time for a job of several passes and parts | Requires the weld length per pass, or the pipe outside diameter for a pipe butt weld, and the travel speed |
| Weld length | Finds the length welded in one continuous pass | Requires the travel speed and the arc-on travel time |
| Travel speed | Finds the average travel speed of one continuous pass | Requires the weld length per pass and the arc-on travel time |
Length can be entered in inches or millimetres, speed in in/min or mm/min, and time in minutes, seconds or hours. Welding time has a Weld type setting: Straight or seam weld takes a length, and Pipe butt weld takes the pipe outside diameter and uses one trip around the pipe as the pass length. Its optional Job assumptions are the passes per part, the number of parts and a measured arc-on factor, which are 1 pass, 1 part and 100% unless changed.
Welding Time Formulas
| T | Arc-on time for one pass on one part (minutes) |
| L | Weld length per pass (inches). For a pipe butt weld, L = ฯ ร outside diameter |
| S | Travel speed (inches per minute) |
Welding time
parts
Working time = arc time รท F
F is the arc-on factor as a decimal: the share of the welder’s working time in which the arc is burning. A 30 inch seam at 5 in/min takes 30 รท 5 = 6 minutes of arc time, and 5 inches at 18 in/min takes 0.278 minutes, or 16.7 seconds. For a 6.625 inch outside diameter pipe at 4 in/min, one pass is ฯ ร 6.625 = 20.81 inches and takes 5.20 minutes. Three passes on each of 10 joints is 156.1 minutes of arc time, and at a 30% arc-on factor the working time is 156.1 รท 0.30 = 520.3 minutes, or 8.67 hours.
How to Calculate Welding Time
- Measure the length of one pass. For a joint around a pipe, multiply the outside diameter by ฯ.
- Divide that length by the travel speed from the welding procedure to get the arc time for one pass.
- Multiply by the number of passes per part and by the number of parts.
- Divide by the arc-on factor to allow for the time the arc is off.
The arc-on factor is also called the operating factor or duty cycle. Published ranges are 15% to 30% for stick welding (SMAW), 25% to 40% for TIG (GTAW), 30% to 45% for MIG/MAG (GMAW), 25% to 45% for flux-cored welding (FCAW) and 80% to 95% for submerged arc welding (SAW). These ranges cover tacking, slag removal, electrode changes, repositioning and rest breaks, but not set-up or assembly time [1].
Weld length
At 12 in/min for 4 minutes of arc time, L = 12 ร 4 = 48 inches. This function and Travel speed work on one continuous pass, without the job assumptions.
Travel speed
The welding travel speed formula is the weld length divided by the arc time. A 36 inch pass that takes 4.5 minutes averages 36 รท 4.5 = 8 in/min, which is 203.2 mm/min.
Limits of This Estimate
- Travel speed is treated as constant, and every pass is given the same length and speed. Passes that differ need separate estimates.
- The calculator does not choose a travel speed or the number of passes. Both come from the welding procedure for the joint, material and process.
- The arc-on factor here is a share of working time. It is not the rated duty cycle printed on a welding machine, and the published ranges shift with the shop and the job [1].
- Working time covers only the activities measured in the arc-on factor. Fit-up, preheat, inspection and repair are extra.
Sources
- TWI, Job Knowledge 96, Welding costs: definition of the operating factor and its ranges by welding process