Calculate earned value schedule variance, its percentage, and the schedule performance index, or solve for earned and planned value using a consistent budget basis.

Compare the budgeted value of completed work with planned work.

Use one budget baseline and status date. Changing the budget basis reinterprets the entered amounts; it does not convert them.

Budgeted value of work completed, not actual cost.

Budgeted value of work planned by the same date.

Schedule Variance Guide

Schedule variance (SV) is an earned value management metric that compares the value of work actually completed with the value of work that was planned to be completed by the same status date. This calculator can solve for SV, BCWP, or BCWS when any two values are known.

SV = BCWP - BCWS
Term Meaning Common Alias Unit
BCWP Budgeted cost of work performed to date Earned Value (EV) Budgeted currency, hours, or work units
BCWS Budgeted cost of work scheduled by the status date Planned Value (PV) Budgeted currency, hours, or work units
SV Difference between earned value and planned value Schedule Variance Budgeted currency, hours, or work units

How to Interpret the Result

SV Result What It Means Practical Interpretation
Positive More earned work than planned More planned work value has been completed than expected by the status date.
Zero Earned value matches plan Completed work value matches the plan exactly at that checkpoint.
Negative Less earned work than planned Less planned work value has been completed than expected by the status date.

Rearranged Forms

If you need to solve for one of the inputs instead of schedule variance, use these forms:

BCWP = SV + BCWS
BCWS = BCWP - SV

How to Calculate Schedule Variance

  1. Set a single project status date.
  2. Determine the budgeted value of the work actually completed by that date.
  3. Determine the budgeted value of the work that should have been completed by that date.
  4. Subtract the scheduled value from the performed value.

Example Calculation

If the project has earned $48,000 of budgeted work but was scheduled to have earned $52,000 by the same checkpoint:

SV = 48,000 - 52,000 = - 4,000

An SV of -$4,000 means the project is behind schedule in earned value terms.

Important Notes

  • Use the same status date for both BCWP and BCWS.
  • Use the same baseline budget for both values.
  • Keep all inputs on the same budget basis: currency, budgeted labor hours, or consistent budgeted work units. Changing the calculatorโ€™s basis reinterprets the amounts; it does not convert them.
  • Schedule variance is a value-based measure, not a direct measure of calendar days or critical-path status. SV is defined when PV is zero, but SV percentage and SPI are not because they divide by PV.
  • A negative schedule variance does not automatically mean the project is over budget.

Best Uses for This Calculator

  • Weekly or monthly project performance reviews
  • Earned value reporting dashboards
  • Comparing planned progress against actual progress
  • Flagging schedule slippage early enough to take corrective action

Common Questions

Why is schedule variance shown in dollars instead of time?
Because the metric compares budgeted value earned versus budgeted value planned, giving heavier weight to higher-value work.

Does a positive SV always mean the project is healthy?
It means more budgeted work value has been earned than planned at that checkpoint. Review the critical path, cost, quality, and scope separately; SV can return to zero at full completion even if the project finished late.

Can schedule variance be exactly zero?
Yes. A result of $0 means the earned value matches the planned value at the selected status date.